2022
INSTALLATION OF 80kVA ONLINE UPS AT North West University
North West University (Gidan Ado Bayero City Campus)
80kva ups integrated with seperate charge controller and solar panels to power 2 elevators for 11 floor building
Solar & Renewable
12kva DEYE 3phase hybrid inverter synchronized to give 24kwp to power water treatments machines RO and and other equipment in the factory.

Load study
Roof accessment
Inverter installation
Panel installation
Distribution
Commissioning
24kva kVA
inverter Capacity
Ring road rijiyan zaki
kano
Protected
Critical Uptime
The factory suffer from fueling diesel on there generators, noice pollution downtime for engine maintenance etc
We carried out load accessment payback time and roof availability on the site.
The factory is now working fully in solar during the day time, and cut off the diesel purchase to 95%
On site
Photography from the installation, commissioning and handover.
More work

2022
North West University (Gidan Ado Bayero City Campus)
80kva ups integrated with seperate charge controller and solar panels to power 2 elevators for 11 floor building

2026

2026
Share your project and our engineers will come back with sizing, scope and a clear quote, no obligation.